Description
|
Unit
|
Total Scope
|
Progress in March 2011
|
Total Progress incl. March 2011
|
Pile
|
Nos.
|
618
|
Completed | |
Pile cap
|
Nos.
|
139
|
Completed | |
Pier/Abutment
|
Nos.
|
147
|
Completed | |
Segment casting
|
Nos.
|
2342
|
Completed | |
Segment erection
|
Span
|
125
|
Completed | |
| Bandra Cable Stay P19 | Lifts | 84 | Completed | |
| Worli Cable Stay P27 | Lifts | 36 | Completed | |
| Worli Cable Stay P30 | Lifts | 34 | Completed | |
| Finishing Works (SB) | % | 100 | 0 | 88 |
| Finishing Works (NB) | % | 100 | 0 | 72 |
| Finishing Works Toll plaza | % | 100 | 0 | 98 |
North carriageway opened to traffic from 24/03/10
.
| Completed Bridge (SB) | Bridge Balance (SB) |